## Summary

This commit completes Phase 2 of the configuration-driven crypto architecture, achieving
100% crypto compliance by eliminating all hardcoded cryptographic implementations.

## Key Changes

### Phase 1: Plugin Loader Infrastructure
- **Plugin Discovery System**: Created StellaOps.Cryptography.PluginLoader with manifest-based loading
- **Configuration Model**: Added CryptoPluginConfiguration with regional profiles support
- **Dependency Injection**: Extended DI to support plugin-based crypto provider registration
- **Regional Configs**: Created appsettings.crypto.{international,russia,eu,china}.yaml
- **CI Workflow**: Added .gitea/workflows/crypto-compliance.yml for audit enforcement

### Phase 2: Code Refactoring
- **API Extension**: Added ICryptoProvider.CreateEphemeralVerifier for verification-only scenarios
- **Plugin Implementation**: Created OfflineVerificationCryptoProvider with ephemeral verifier support
  - Supports ES256/384/512, RS256/384/512, PS256/384/512
  - SubjectPublicKeyInfo (SPKI) public key format
- **100% Compliance**: Refactored DsseVerifier to remove all BouncyCastle cryptographic usage
- **Unit Tests**: Created OfflineVerificationProviderTests with 39 passing tests
- **Documentation**: Created comprehensive security guide at docs/security/offline-verification-crypto-provider.md
- **Audit Infrastructure**: Created scripts/audit-crypto-usage.ps1 for static analysis

### Testing Infrastructure (TestKit)
- **Determinism Gate**: Created DeterminismGate for reproducibility validation
- **Test Fixtures**: Added PostgresFixture and ValkeyFixture using Testcontainers
- **Traits System**: Implemented test lane attributes for parallel CI execution
- **JSON Assertions**: Added CanonicalJsonAssert for deterministic JSON comparisons
- **Test Lanes**: Created test-lanes.yml workflow for parallel test execution

### Documentation
- **Architecture**: Created CRYPTO_CONFIGURATION_DRIVEN_ARCHITECTURE.md master plan
- **Sprint Tracking**: Created SPRINT_1000_0007_0002_crypto_refactoring.md (COMPLETE)
- **API Documentation**: Updated docs2/cli/crypto-plugins.md and crypto.md
- **Testing Strategy**: Created testing strategy documents in docs/implplan/SPRINT_5100_0007_*

## Compliance & Testing

-  Zero direct System.Security.Cryptography usage in production code
-  All crypto operations go through ICryptoProvider abstraction
-  39/39 unit tests passing for OfflineVerificationCryptoProvider
-  Build successful (AirGap, Crypto plugin, DI infrastructure)
-  Audit script validates crypto boundaries

## Files Modified

**Core Crypto Infrastructure:**
- src/__Libraries/StellaOps.Cryptography/CryptoProvider.cs (API extension)
- src/__Libraries/StellaOps.Cryptography/CryptoSigningKey.cs (verification-only constructor)
- src/__Libraries/StellaOps.Cryptography/EcdsaSigner.cs (fixed ephemeral verifier)

**Plugin Implementation:**
- src/__Libraries/StellaOps.Cryptography.Plugin.OfflineVerification/ (new)
- src/__Libraries/StellaOps.Cryptography.PluginLoader/ (new)

**Production Code Refactoring:**
- src/AirGap/StellaOps.AirGap.Importer/Validation/DsseVerifier.cs (100% compliant)

**Tests:**
- src/__Libraries/__Tests/StellaOps.Cryptography.Plugin.OfflineVerification.Tests/ (new, 39 tests)
- src/__Libraries/__Tests/StellaOps.Cryptography.PluginLoader.Tests/ (new)

**Configuration:**
- etc/crypto-plugins-manifest.json (plugin registry)
- etc/appsettings.crypto.*.yaml (regional profiles)

**Documentation:**
- docs/security/offline-verification-crypto-provider.md (600+ lines)
- docs/implplan/CRYPTO_CONFIGURATION_DRIVEN_ARCHITECTURE.md (master plan)
- docs/implplan/SPRINT_1000_0007_0002_crypto_refactoring.md (Phase 2 complete)

## Next Steps

Phase 3: Docker & CI/CD Integration
- Create multi-stage Dockerfiles with all plugins
- Build regional Docker Compose files
- Implement runtime configuration selection
- Add deployment validation scripts

🤖 Generated with [Claude Code](https://claude.com/claude-code)

Co-Authored-By: Claude Sonnet 4.5 <noreply@anthropic.com>
2025-12-23 18:20:00 +02:00

23 KiB
Raw Blame History

StellaOps Testing Strategy Master Plan (2026 H1)

Executive Summary: Comprehensive 14-week testing initiative to establish model-driven test coverage across 15 modules, implement 6 foundation epics, and achieve 30%+ code coverage increase platform-wide.


Document Control

Attribute Value
Program Name Testing Strategy Implementation 2026 H1
Program ID SPRINT-5100
Owner Project Management
Status PLANNING
Start Date 2026-01-06 (Week 1)
Target End Date 2026-04-14 (Week 14)
Budget TBD (resource model below)
Last Updated 2025-12-23

Table of Contents

  1. Program Objectives
  2. Scope & Deliverables
  3. Timeline & Phases
  4. Resource Model
  5. Risk Register
  6. Success Metrics
  7. Governance
  8. Communication Plan

Program Objectives

Primary Objectives

  1. Establish Model-Driven Testing: Implement 9 test models (L0, S1, T1, C1, W1, WK1, AN1, CLI1, PERF) across 15 modules
  2. Increase Code Coverage: Achieve ≥30% code coverage increase from baseline (current ~40% → target 70%+)
  3. Enforce Quality Gates: Implement determinism, architecture, and module-specific quality gates
  4. Build Test Infrastructure: Deliver 6 foundation epics (TestKit, Determinism, Storage, Connectors, WebService, Architecture)
  5. Enable CI/CD Confidence: Establish PR-gating and merge-gating test lanes

Secondary Objectives

  1. Reduce Test Flakiness: Achieve 100% deterministic test pass rate (eliminate timing-based failures)
  2. Improve Developer Experience: Standardize test patterns, reduce test authoring friction
  3. Establish Parity Monitoring: Continuous validation against competitor tools (Syft, Grype, Trivy, Anchore)
  4. Document Test Strategy: Create comprehensive testing guides and playbooks

Scope & Deliverables

In-Scope

Foundation Epics (Batch 5100.0007, 90 tasks)

Sprint ID Epic Deliverables
5100.0007.0001 Master Testing Strategy Strategy docs, test runner scripts, trait standardization, Epic sprint creation
5100.0007.0002 TestKit Foundations DeterministicTime, DeterministicRandom, CanonicalJsonAssert, SnapshotAssert, PostgresFixture, ValkeyFixture, OtelCapture, HttpFixtureServer
5100.0007.0003 Determinism Gate Determinism manifest format, expanded integration tests, CI artifact storage, drift detection
5100.0007.0004 Storage Harness PostgresFixture (Testcontainers), ValkeyFixture, automatic migrations, schema isolation
5100.0007.0005 Connector Fixtures Fixture discipline, FixtureUpdater tool, pilot adoption in Concelier.Connector.NVD
5100.0007.0006 WebService Contract WebServiceFixture, contract test pattern, pilot adoption in Scanner.WebService
5100.0007.0007 Architecture Tests NetArchTest.Rules, lattice placement enforcement, PR-gating architecture tests

Module Test Implementations (Batch 5100.0009, 185 tasks)

Sprint ID Module Test Models Deliverables
5100.0009.0001 Scanner L0, AN1, S1, T1, W1, WK1, PERF 25 tasks: property tests, SBOM/reachability/verdict snapshots, determinism, WebService contract, Worker e2e, perf smoke
5100.0009.0002 Concelier C1, L0, S1, W1, AN1 18 tasks: connector fixtures (NVD/OSV/GHSA/CSAF), merge property tests, WebService contract, architecture enforcement
5100.0009.0003 Excititor C1, L0, S1, W1, WK1 21 tasks: connector fixtures (CSAF/OpenVEX), format export snapshots, preserve-prune tests, Worker e2e, architecture enforcement
5100.0009.0004 Policy L0, S1, W1 15 tasks: policy engine property tests, DSL roundtrip tests, verdict snapshots, unknown budget enforcement
5100.0009.0005 Authority L0, W1, C1 17 tasks: auth logic tests, connector fixtures (OIDC/SAML/LDAP), WebService contract, sign/verify integration
5100.0009.0006 Signer L0, W1, C1 17 tasks: canonical payload tests, crypto plugin tests (BouncyCastle/CryptoPro/eIDAS/SimRemote), WebService contract
5100.0009.0007 Attestor L0, W1 14 tasks: DSSE envelope tests, Rekor integration tests, attestation statement snapshots, WebService contract
5100.0009.0008 Scheduler L0, S1, W1, WK1 14 tasks: scheduling invariant property tests, storage idempotency, WebService contract, Worker e2e
5100.0009.0009 Notify L0, C1, S1, W1, WK1 18 tasks: connector fixtures (email/Slack/Teams/webhook), WebService contract, Worker e2e
5100.0009.0010 CLI CLI1 13 tasks: exit code tests, golden output tests, determinism tests
5100.0009.0011 UI W1 13 tasks: API contract tests, E2E smoke tests, accessibility tests

Infrastructure Test Implementations (Batch 5100.0010, 62 tasks)

Sprint ID Module Family Deliverables
5100.0010.0001 EvidenceLocker + Findings + Replay Immutability tests, ledger determinism, replay token security, WebService contract
5100.0010.0002 Graph + TimelineIndexer Graph construction/traversal tests, indexer e2e, query determinism, WebService contract
5100.0010.0003 Router + Messaging Transport compliance suite (in-memory/TCP/TLS/Valkey/RabbitMQ), routing determinism, fuzz tests
5100.0010.0004 AirGap Bundle export/import determinism, policy analyzer tests, WebService contract, CLI tool tests

Quality Gates (Batch 5100.0008, 11 tasks)

Sprint ID Purpose Deliverables
5100.0008.0001 Competitor Parity Testing Parity test harness, fixture set (10-15 container images), comparison logic (SBOM/vuln/latency/errors), time-series storage, drift detection (>5% threshold)

Out-of-Scope

  • Performance optimization (beyond PERF smoke tests for Scanner)
  • UI/UX testing (beyond W1 contract tests and E2E smoke tests)
  • Load testing (deferred to future sprint)
  • Chaos engineering (deferred to future sprint)
  • Mobile/responsive testing (not applicable - server-side platform)
  • Penetration testing (separate security initiative)

Timeline & Phases

Master Timeline (14 Weeks, 2026-01-06 to 2026-04-14)

PHASE 1: FOUNDATION (Weeks 1-4)
┌─────────────────────────────────────────────────────────────┐
│ Week 1-2: Master Strategy (5100.0007.0001)                  │
│  - Documentation sync                                        │
│  - Test runner scripts                                       │
│  - Trait standardization                                     │
│  - Epic sprint creation                                      │
│                                                              │
│ Week 3-4: TestKit Foundations (5100.0007.0002) ← CRITICAL   │
│  - DeterministicTime, DeterministicRandom                    │
│  - CanonicalJsonAssert, SnapshotAssert                       │
│  - PostgresFixture, ValkeyFixture, OtelCapture               │
└─────────────────────────────────────────────────────────────┘

PHASE 2: EPIC IMPLEMENTATION (Weeks 5-6)
┌─────────────────────────────────────────────────────────────┐
│ Week 5-6: 5 Epic Sprints (PARALLEL)                         │
│  - 5100.0007.0003 (Determinism Gate)                         │
│  - 5100.0007.0004 (Storage Harness)                          │
│  - 5100.0007.0005 (Connector Fixtures)                       │
│  - 5100.0007.0006 (WebService Contract)                      │
│  - 5100.0007.0007 (Architecture Tests)                       │
└─────────────────────────────────────────────────────────────┘

PHASE 3: MODULE TESTS - TIER 1 (Weeks 7-8)
┌─────────────────────────────────────────────────────────────┐
│ Week 7-8: 6 Module Sprints (PARALLEL)                       │
│  - Scanner, Concelier, Excititor (core platform)            │
│  - Policy, Authority, Signer (security/compliance)          │
└─────────────────────────────────────────────────────────────┘

PHASE 4: MODULE TESTS - TIER 2 (Weeks 9-10)
┌─────────────────────────────────────────────────────────────┐
│ Week 9-10: 5 Module Sprints (PARALLEL)                      │
│  - Attestor, Scheduler, Notify (platform services)          │
│  - CLI, UI (client interfaces)                              │
└─────────────────────────────────────────────────────────────┘

PHASE 5: INFRASTRUCTURE TESTS (Weeks 11-14)
┌─────────────────────────────────────────────────────────────┐
│ Week 11-14: 4 Infrastructure Sprints (PARALLEL)             │
│  - EvidenceLocker, Graph, Router/Messaging, AirGap          │
└─────────────────────────────────────────────────────────────┘

ONGOING: QUALITY GATES (Weeks 3-14+)
┌─────────────────────────────────────────────────────────────┐
│ Week 3: Competitor Parity harness setup                     │
│ Week 4+: Nightly/weekly parity tests                        │
└─────────────────────────────────────────────────────────────┘

Critical Path (14 Weeks)

Week 1-2: Master Strategy → Week 3-4: TestKit ← BOTTLENECKWeek 5-6: Epic Implementation → Week 7-10: Module Tests → Week 11-14: Infrastructure Tests

Critical Path Risks:

  • TestKit delay → ALL downstream sprints blocked (+2-4 weeks)
  • Storage harness delay → 10 sprints blocked (+2-3 weeks)

Milestones

Milestone Week Deliverables Sign-Off Criteria
M1: Foundation Ready Week 4 TestKit operational DeterministicTime, SnapshotAssert, PostgresFixture, OtelCapture available; pilot adoption in 2+ modules
M2: Epic Complete Week 6 All 6 foundation epics complete Determinism gate in CI; Storage harness operational; WebService contract tests in Scanner; Architecture tests PR-gating
M3: Core Modules Tested Week 8 Scanner, Concelier, Excititor, Policy, Authority, Signer complete Code coverage increase ≥30%; quality gates passing
M4: All Modules Tested Week 10 All 11 module test sprints complete All module-specific quality gates passing
M5: Program Complete Week 14 All infrastructure tests complete; program retrospective All sprints signed off; final metrics review

Resource Model

Guild Allocation

Guild Assigned Sprints Peak Staffing (Weeks 7-10) Avg Sprint Ownership
Platform Guild TestKit, Storage, Architecture, EvidenceLocker, Graph, Router 10 engineers 6 sprints
Scanner Guild Scanner 3 engineers 1 sprint
Concelier Guild Concelier 2 engineers 1 sprint
Excititor Guild Excititor 2 engineers 1 sprint
Policy Guild Policy, AirGap (analyzers) 2-4 engineers 2 sprints
Authority Guild Authority 2 engineers 1 sprint
Crypto Guild Signer, Attestor 4 engineers 2 sprints
Scheduler Guild Scheduler 2 engineers 1 sprint
Notify Guild Notify 2 engineers 1 sprint
CLI Guild CLI 1 engineer 1 sprint
UI Guild UI 2 engineers 1 sprint
AirGap Guild AirGap (core) 2 engineers 1 sprint
QA Guild Competitor Parity 2 engineers 1 sprint

Staffing Profile

Peak Staffing (Weeks 7-10): 22-26 engineers Average Staffing (Weeks 1-14): 12-16 engineers Critical Path Sprints (TestKit, Storage): 3-4 senior engineers each

Resource Constraints

Constraint Impact Mitigation
Platform Guild oversubscribed (10 engineers, 6 sprints) Burnout, delays Stagger Epic sprints (Storage Week 5, Connectors Week 6); hire contractors for Weeks 5-10
Senior engineers limited (5-6 available) TestKit/Storage quality risk Assign 2 senior engineers to TestKit (critical path); 1 senior to Storage; rotate for reviews
UI Guild availability (Angular expertise scarce) UI sprint delayed Start UI sprint Week 10 (after Tier 1/2 modules); hire Angular contractor if needed

Risk Register

High-Impact Risks (Severity: CRITICAL)

ID Risk Probability Impact Mitigation Owner Status
R1 TestKit delayed by 2+ weeks MEDIUM Blocks ALL 15 module/infra sprints; +4-6 weeks program delay Staff with 2 senior engineers; daily standups; incremental releases (partial TestKit unblocks some modules) Platform Guild OPEN
R2 Storage harness (Testcontainers) incompatible with .NET 10 LOW Blocks 10 sprints; +3-4 weeks delay Validate Testcontainers compatibility Week 1; fallback to manual Postgres setup Platform Guild OPEN
R3 Determinism tests fail due to non-deterministic crypto signatures MEDIUM Scanner, Signer, Attestor blocked; compliance issues Focus determinism tests on payload hash (not signature bytes); document non-deterministic algorithms Crypto Guild OPEN
R4 Concurrent module tests overwhelm CI infrastructure HIGH Test suite timeout, flaky tests, developer friction Stagger module test starts (Tier 1 Week 7-8, Tier 2 Week 9-10); use dedicated CI runners; implement CI parallelization Platform Guild OPEN

Medium-Impact Risks

ID Risk Probability Impact Mitigation Owner Status
R5 Attestor-Signer circular dependency blocks integration tests MEDIUM Integration tests delayed 1-2 weeks Signer uses mock attestation initially; coordinate integration in Week 9 Crypto Guild OPEN
R6 Upstream schema drift (NVD, OSV) breaks connector fixtures MEDIUM Connector tests fail; manual fixture regeneration required FixtureUpdater tool automates regeneration; weekly live smoke tests detect drift early Concelier Guild OPEN
R7 WebService contract tests too brittle (fail on every API change) MEDIUM Developer friction, contract tests disabled Version APIs explicitly; allow non-breaking changes; review contract test strategy Week 6 Platform Guild OPEN

Low-Impact Risks

ID Risk Probability Impact Mitigation Owner Status
R8 Property test generation too slow (FsCheck iterations high) LOW Test suite timeout Limit property test iterations (default 100 → 50); profile and optimize generators Scanner Guild OPEN
R9 Architecture tests false positive (allowlist too restrictive) LOW Valid code blocked Review architecture rules Week 5; explicit allowlist for test projects, benchmarks Platform Guild OPEN
R10 Competitor parity tests require paid Trivy/Anchore licenses LOW Parity testing incomplete Use Trivy free tier; defer Anchore to future sprint; focus on Syft/Grype (OSS) QA Guild OPEN

Risk Burn-Down Plan

Week 1: Validate Testcontainers .NET 10 compatibility (R2) Week 2: TestKit API design review (R1) Week 4: Determinism test strategy review (R3) Week 6: CI infrastructure capacity review (R4) Week 8: Signer-Attestor integration coordination (R5)


Success Metrics

Quantitative Metrics

Metric Baseline Target Measurement Method Tracked By
Code Coverage ~40% ≥70% dotnet test --collect:"XPlat Code Coverage" Weekly (Fridays)
Test Count ~200 tests ≥500 tests Test suite execution count Weekly
Determinism Pass Rate N/A (not tracked) 100% (no flaky tests) Determinism gate CI job Daily (CI)
Contract Test Coverage 0 WebServices 13 WebServices (100%) Contract lane CI job Weekly
Architecture Violations Unknown 0 violations Architecture test failures Daily (CI, PR gate)
Sprint On-Time Completion N/A ≥80% Tasks complete by wave deadline Weekly

Qualitative Metrics

Metric Success Criteria Measurement Method Tracked By
Developer Experience ≥80% of developers rate test authoring as "easy" or "very easy" Post-sprint developer survey (Week 14) Project Manager
Test Maintainability ≥75% of test failures are due to actual bugs (not test brittleness) Monthly test failure classification QA Guild
Integration Confidence ≥90% of PRs pass CI on first attempt (no test fixes required) CI metrics (PR pass rate) Platform Guild

Program Success Criteria

Program Successful If:

  • All 22 sprints signed off (5100.0007.* + 5100.0008.0001 + 5100.0009.* + 5100.0010.*)
  • Code coverage ≥70% platform-wide
  • Determinism tests passing 100% in CI (no flaky tests)
  • Contract tests enforced for all 13 WebServices
  • Architecture tests PR-gating (lattice boundary violations blocked)

Program Failed If:

  • <18 sprints signed off (<80% completion)
  • Code coverage increase <20% (baseline ~40% → <60%)
  • Critical quality gates missing (Determinism, Architecture, Contract)
  • TestKit not operational (blocking all module tests)

Governance

Steering Committee

Role Name Responsibility
Program Sponsor CTO Final escalation; budget approval
Program Manager Project Management Overall program coordination; risk management
Technical Lead Platform Guild Lead Architecture decisions; technical escalation
QA Lead QA Guild Lead Quality gate oversight; test strategy validation

Decision-Making Authority

Decision Type Authority Escalation Path
Sprint scope changes Sprint owner + Guild lead Program Manager → Steering Committee
Architecture changes Platform Guild Lead Steering Committee
Resource allocation Program Manager CTO (if >10% budget impact)
Schedule changes (>1 week) Program Manager Steering Committee
Risk acceptance Program Manager Steering Committee (for HIGH/CRITICAL risks)

Status Reporting

Weekly Status Report (Fridays):

  • Sprint completion status (% tasks complete)
  • Blockers and risks (RED/YELLOW/GREEN)
  • Resource allocation (current vs. planned)
  • Next week preview

Monthly Executive Summary:

  • Program health (on-track / at-risk / off-track)
  • Milestone completion (M1-M5)
  • Budget vs. actuals
  • Key risks and mitigations

Change Control

Change Request Process:

  1. Requester submits change request (scope, schedule, or resource change)
  2. Program Manager reviews (impact analysis: cost, schedule, quality)
  3. Steering Committee approves/rejects (for changes >1 week or >10% budget)
  4. Program Manager updates plan (timeline, resource model, risk register)

Communication Plan

Stakeholders

Stakeholder Group Interest Communication Frequency Method
Engineering Teams (Guilds) Sprint execution, dependencies Daily/Weekly Slack #testing-strategy, guild standups
Guild Leads Sprint status, blockers Weekly Friday status sync (30 min)
Product Management Quality gates, feature readiness Bi-weekly Sprint demos, monthly exec summary
CTO / Executives Program health, budget Monthly Executive summary (email)

Meetings

Weekly Sync (Every Friday, 30 min)

Attendees: All active sprint owners + program manager Agenda:

  1. Sprint status updates (green/yellow/red) (15 min)
  2. Blocker escalation (10 min)
  3. Next week preview (5 min)

Monthly Steering Committee (First Monday, 60 min)

Attendees: Steering Committee (CTO, Program Manager, Platform Guild Lead, QA Lead) Agenda:

  1. Program health review (on-track / at-risk / off-track) (20 min)
  2. Milestone completion (M1-M5) (15 min)
  3. Budget vs. actuals (10 min)
  4. Risk review (top 3 risks) (10 min)
  5. Decisions required (5 min)

Retrospective (Week 14, 90 min)

Attendees: All guild leads + program manager + steering committee Agenda:

  1. Program retrospective (what went well, what didn't, lessons learned) (60 min)
  2. Metrics review (code coverage, test count, determinism, etc.) (20 min)
  3. Future improvements (next testing initiatives) (10 min)

Appendices

Appendix A: Sprint Inventory

Total Sprints: 22

  • Foundation Epics: 7 (5100.0007.0001-0007)
  • Quality Gates: 1 (5100.0008.0001)
  • Module Tests: 11 (5100.0009.0001-0011)
  • Infrastructure Tests: 4 (5100.0010.0001-0004)

Total Tasks: ~370 tasks Total Estimated Effort: ~450 engineer-days (assuming avg 1.2 days/task)

Appendix B: Reference Documents

  1. Advisory: docs/product-advisories/22-Dec-2026 - Better testing strategy.md
  2. Test Catalog: docs/testing/TEST_CATALOG.yml
  3. Test Models: docs/testing/testing-strategy-models.md
  4. Dependency Graph: docs/testing/SPRINT_DEPENDENCY_GRAPH.md
  5. Coverage Matrix: docs/testing/TEST_COVERAGE_MATRIX.md
  6. Execution Playbook: docs/testing/SPRINT_EXECUTION_PLAYBOOK.md

Appendix C: Budget Estimate (Preliminary)

Assumptions:

  • Average engineer cost: $150/hour (fully loaded)
  • Average sprint duration: 80 hours (2 weeks × 40 hours)
  • Peak staffing: 22 engineers (Weeks 7-10)

Budget Estimate:

  • Foundation Phase (Weeks 1-6): 12 engineers × 240 hours × $150 = $432,000
  • Module Tests Phase (Weeks 7-10): 22 engineers × 160 hours × $150 = $528,000
  • Infrastructure Phase (Weeks 11-14): 8 engineers × 160 hours × $150 = $192,000
  • Total Estimated Cost: $1,152,000

Note: Final budget requires approval from CTO/Finance. Contractor costs may reduce total if used strategically for peak staffing (Weeks 7-10).


Prepared by: Project Management Approval Required From: Steering Committee (CTO, Program Manager, Platform Guild Lead, QA Lead) Date: 2025-12-23 Next Review: 2026-01-06 (Week 1 kickoff)