Sprint 5100 - Active Status Report
Generated: 2025-12-22 Epic: Testing Infrastructure & Reproducibility
Overview
Sprint 5100 consists of 12 sprints across 5 phases. Phases 0 and 1 are complete (7 sprints, 51 tasks). Phases 2-5 remain to be implemented (5 sprints, 31 tasks).
Completed and Archived ✅
Location: docs/implplan/archived/sprint_5100_phase_0_1_completed/
- Phase 0 (Harness & Corpus Foundation): 4 sprints, 31 tasks - DONE
- Phase 1 (Determinism & Replay): 3 sprints, 20 tasks - DONE
See archived README for details.
Active Sprints (TODO)
Phase 2: Offline E2E & Interop (2 sprints, 13 tasks)
SPRINT_5100_0003_0001 - SBOM Interop Round-Trip
Status: TODO (0/7 tasks)
Working Directory: tests/interop/ and src/__Libraries/StellaOps.Interop/
Dependencies: Sprint 5100.0001.0002 (Evidence Index) ✅
Tasks:
- T1: Interop Test Harness - TODO
- T2: CycloneDX 1.6 Round-Trip Tests - TODO
- T3: SPDX 3.0.1 Round-Trip Tests - TODO
- T4: Cross-Tool Findings Parity Analysis - TODO
- T5: Interop CI Pipeline - TODO
- T6: Interop Documentation - TODO
- T7: Project Setup - TODO
Goal: Achieve 95%+ parity with Syft/Grype for SBOM generation and vulnerability findings.
SPRINT_5100_0003_0002 - No-Egress Test Enforcement
Status: TODO (0/6 tasks)
Working Directory: tests/offline/ and .gitea/workflows/
Dependencies: Sprint 5100.0001.0003 (Offline Bundle Manifest) ✅
Tasks:
- T1: Network Isolation Test Base Class - TODO
- T2: Docker Network Isolation - TODO
- T3: Offline E2E Test Suite - TODO
- T4: CI Network Isolation Workflow - TODO
- T5: Offline Bundle Fixtures - TODO
- T6: Unit Tests - TODO
Goal: Prove air-gap operation with strict network isolation enforcement.
Phase 3: Unknowns Budgets CI Gates (1 sprint, 6 tasks)
SPRINT_5100_0004_0001 - Unknowns Budget CI Gates
Status: TODO (0/6 tasks)
Working Directory: src/Cli/StellaOps.Cli/Commands/ and .gitea/workflows/
Dependencies: Sprint 4100.0001.0001 (Reason-Coded Unknowns), Sprint 4100.0001.0002 (Unknown Budgets)
Tasks:
- T1: CLI Budget Check Command - TODO
- T2: CI Budget Gate Workflow - TODO
- T3: GitHub/GitLab PR Integration - TODO
- T4: Unknowns Dashboard Integration - TODO
- T5: Attestation Integration - TODO
- T6: Unit Tests - TODO
Goal: Enforce unknowns budgets in CI/CD pipelines with PR integration.
Phase 4: Backpressure & Chaos (1 sprint, 6 tasks)
SPRINT_5100_0005_0001 - Router Chaos Suite
Status: TODO (0/6 tasks)
Working Directory: tests/load/ and tests/chaos/
Dependencies: Router implementation with backpressure (existing)
Tasks:
- T1: Load Test Harness - TODO
- T2: Backpressure Verification Tests - TODO
- T3: Recovery and Resilience Tests - TODO
- T4: Valkey Failure Injection - TODO
- T5: CI Chaos Workflow - TODO
- T6: Documentation - TODO
Goal: Validate 429/503 responses, Retry-After headers, and sub-30s recovery under load.
Phase 5: Audit Packs & Time-Travel (1 sprint, 6 tasks)
SPRINT_5100_0006_0001 - Audit Pack Export/Import
Status: TODO (0/6 tasks)
Working Directory: src/__Libraries/StellaOps.AuditPack/ and src/Cli/StellaOps.Cli/Commands/
Dependencies: Sprint 5100.0001.0001 (Run Manifest) ✅, Sprint 5100.0002.0002 (Replay Runner) ✅
Tasks:
- T1: Audit Pack Domain Model - TODO
- T2: Audit Pack Builder - TODO
- T3: Audit Pack Importer - TODO
- T4: Replay from Audit Pack - TODO
- T5: CLI Commands - TODO
- T6: Unit and Integration Tests - TODO
Goal: Enable sealed audit pack export for compliance with one-command replay verification.
Recommended Implementation Order
Based on dependencies and value delivery:
- SPRINT_5100_0003_0001 (SBOM Interop) - No blockers, high value for ecosystem compatibility
- SPRINT_5100_0003_0002 (No-Egress) - Parallel with above, proves air-gap capability
- SPRINT_5100_0006_0001 (Audit Packs) - Dependencies met, critical for compliance
- SPRINT_5100_0004_0001 (Unknowns Budgets) - Depends on Sprint 4100 completion
- SPRINT_5100_0005_0001 (Router Chaos) - Independent, can run in parallel
Success Metrics
- Phase 2: 95%+ SBOM interop parity, air-gap tests pass with no network
- Phase 3: CI gates block on budget violations, PR comments working
- Phase 4: Router handles 50x load spikes with <30s recovery
- Phase 5: Audit packs import/export with replay producing identical verdicts
Next Actions
- Review Phase 2 sprints in detail
- Start with SPRINT_5100_0003_0001 (SBOM Interop Round-Trip)
- Run parallel track for SPRINT_5100_0003_0002 (No-Egress)
- Coordinate with Sprint 4100 team on unknowns budget dependencies