Epic 8200 · SBOM/VEX Pipeline Reproducibility
Overview
This epic implements the reproducibility, verifiability, and audit-readiness requirements identified in the product advisory analysis of December 2024.
Goal: Ensure StellaOps produces byte-for-byte identical outputs given identical inputs, with full attestation and offline verification capabilities.
Epic Timeline
| Phase | Sprints | Duration | Focus |
|---|---|---|---|
| Phase 1: Foundation | 8200.0001.0001 | Week 1 | VerdictId content-addressing (critical fix) |
| Phase 2: Validation | 8200.0001.0002, 8200.0001.0003 | Week 1-2 | DSSE round-trips, schema validation |
| Phase 3: E2E | 8200.0001.0004 | Week 2-3 | Full pipeline reproducibility test |
| Phase 4: Packaging | 8200.0001.0005, 8200.0001.0006 | Week 3 | Sigstore bundles, budget attestation |
Sprint Summary
P0: SPRINT_8200_0001_0001 — Verdict ID Content-Addressing
Status: TODO | Effort: 2 days | Blocks: All other sprints
Problem: DeltaVerdict.VerdictId uses random GUID instead of content hash.
Solution: Implement VerdictIdGenerator using SHA-256 of canonical JSON.
| Task Count | Files Modified | Tests Added |
|---|---|---|
| 12 tasks | 5 files | 4 tests |
Key Deliverables:
VerdictIdGeneratorhelper class- Content-addressed VerdictId in all verdict creation sites
- Regression tests for determinism
P1: SPRINT_8200_0001_0002 — DSSE Round-Trip Testing
Status: TODO | Effort: 3 days | Depends on: P0
Problem: No tests validate sign → verify → re-bundle → re-verify cycle. Solution: Comprehensive round-trip test suite with cosign compatibility.
| Task Count | Files Created | Tests Added |
|---|---|---|
| 20 tasks | 4 files | 15 tests |
Key Deliverables:
DsseRoundtripTestFixturewith key management- Round-trip serialization tests
- Cosign compatibility verification
- Multi-signature envelope handling
P2: SPRINT_8200_0001_0003 — SBOM Schema Validation CI
Status: TODO | Effort: 1 day | Depends on: None
Problem: No external validator confirms schema compliance. Solution: Integrate sbom-utility for CycloneDX 1.6 and SPDX 3.0.1 validation.
| Task Count | Files Created | CI Jobs Added |
|---|---|---|
| 17 tasks | 7 files | 4 jobs |
Key Deliverables:
- Schema files committed to repo
schema-validation.ymlworkflow- Validation scripts for all SBOM formats
- Required PR check
P3: SPRINT_8200_0001_0004 — Full E2E Reproducibility Test
Status: TODO | Effort: 5 days | Depends on: P0, P1
Problem: No test covers full pipeline: ingest → normalize → diff → decide → attest → bundle.
Solution: Create StellaOps.Integration.E2E project with cross-platform verification.
| Task Count | Files Created | CI Jobs Added |
|---|---|---|
| 26 tasks | 8 files | 4 jobs |
Key Deliverables:
- Full pipeline test fixture
- Cross-platform hash comparison (Linux, Windows, macOS)
- Golden baseline fixtures
- Nightly reproducibility gate
P4: SPRINT_8200_0001_0005 — Sigstore Bundle Implementation
Status: TODO | Effort: 3 days | Depends on: P1
Problem: Sigstore bundle type defined but not implemented. Solution: Implement v0.3 bundle marshalling/unmarshalling with offline verification.
| Task Count | Files Created | Tests Added |
|---|---|---|
| 24 tasks | 9 files | 4 tests |
Key Deliverables:
StellaOps.Attestor.BundlelibrarySigstoreBundleBuilderandSigstoreBundleVerifier- cosign bundle compatibility
- CLI command
stella attest bundle
P6: SPRINT_8200_0001_0006 — Budget Threshold Attestation
Status: TODO | Effort: 2 days | Depends on: P0
Problem: Unknown budget thresholds not attested in DSSE bundles.
Solution: Create BudgetCheckPredicate and include in verdict attestations.
| Task Count | Files Created/Modified | Tests Added |
|---|---|---|
| 18 tasks | 7 files | 4 tests |
Key Deliverables:
BudgetCheckPredicatemodel- Budget config hash for determinism
- Integration with
VerdictPredicateBuilder - Verification rule for config drift
Dependency Graph
┌─────────────────┐
│ P0: Verdict │
│ Content-Hash │
└────────┬────────┘
│
┌──────────────┼──────────────┐
│ │ │
▼ ▼ ▼
┌─────────────────┐ ┌─────────────────┐ ┌─────────────────┐
│ P1: DSSE │ │ P2: Schema │ │ P6: Budget │
│ Round-Trip │ │ Validation │ │ Attestation │
└────────┬────────┘ └─────────────────┘ └─────────────────┘
│
┌────────┴────────┐
│ │
▼ ▼
┌─────────────────┐ ┌─────────────────┐
│ P3: E2E Test │ │ P4: Sigstore │
│ │ │ Bundle │
└─────────────────┘ └─────────────────┘
Total Effort Summary
| Sprint | Priority | Effort | Tasks | Status |
|---|---|---|---|---|
| 8200.0001.0001 | P0 | 2 days | 12 | TODO |
| 8200.0001.0002 | P1 | 3 days | 20 | TODO |
| 8200.0001.0003 | P2 | 1 day | 17 | TODO |
| 8200.0001.0004 | P3 | 5 days | 26 | TODO |
| 8200.0001.0005 | P4 | 3 days | 24 | TODO |
| 8200.0001.0006 | P6 | 2 days | 18 | TODO |
| Total | — | 16 days | 117 tasks | — |
Success Criteria
Must Have (Phase 1-2)
- VerdictId is content-addressed (SHA-256)
- DSSE round-trip tests pass
- Schema validation in CI
- All existing tests pass (no regressions)
Should Have (Phase 3)
- Full E2E pipeline test
- Cross-platform reproducibility verified
- Golden baseline established
Nice to Have (Phase 4)
- Sigstore bundle support
- Budget attestation in verdicts
- cosign interoperability
Documentation Deliverables
| Document | Sprint | Status |
|---|---|---|
docs/reproducibility.md |
Pre-req | DONE |
docs/testing/schema-validation.md |
P2 | TODO |
docs/testing/e2e-reproducibility.md |
P3 | TODO |
docs/modules/attestor/bundle-format.md |
P4 | TODO |
docs/modules/policy/budget-attestation.md |
P6 | TODO |
Risk Register
| Risk | Impact | Probability | Mitigation | Owner |
|---|---|---|---|---|
| Breaking change for stored verdicts | High | Medium | Migration logic for old GUID format | Policy Guild |
| Cross-platform determinism failures | High | Medium | Canonical serialization; path normalization | Platform Guild |
| Sigstore spec changes | Medium | Low | Pin to v0.3; monitor upstream | Attestor Guild |
| CI performance impact | Medium | Medium | Parallelize validation jobs | Platform Guild |
Execution Checkpoints
| Checkpoint | Date | Criteria |
|---|---|---|
| Phase 1 Complete | Week 1 end | VerdictId fix merged; tests green |
| Phase 2 Complete | Week 2 end | DSSE round-trips pass; schema validation active |
| Phase 3 Complete | Week 3 end | E2E test running nightly; baselines established |
| Phase 4 Complete | Week 3 end | Sigstore bundles working; budget attestation active |
| Epic Complete | Week 3 end | All success criteria met; docs complete |
Related Documents
- Product Advisory Analysis — Original gap analysis
- Reproducibility Specification — Verdict ID formula and replay procedure
- Determinism Verification — Existing determinism infrastructure
- Attestor Module — DSSE and attestation architecture
Changelog
| Date | Version | Changes |
|---|---|---|
| 2025-12-24 | 1.0 | Initial epic creation based on product advisory gap analysis |