Dossier Sequencing Decision
Decision ID: DECISION-DOCS-001 Status: DEFAULT-APPROVED Effective Date: 2025-12-06 48h Window Started: 2025-12-06T00:00:00Z
Decision
Module dossiers (Md.II through Md.X) are sequenced after Md.I completion, following the dependency chain in docs/implplan/SPRINT_0300_*.md files.
Rationale
- Md.I establishes baseline architecture documentation structure
- Subsequent modules depend on patterns defined in Md.I
- Sequential ordering prevents documentation conflicts
- Allows parallel work within each dossier batch
Sequencing Order
| Phase | Dossiers | Dependencies | Sprint |
|---|---|---|---|
| Md.I | Concelier, Scanner, Authority | None | 0300 |
| Md.II | Attestor, Signer, Evidence | Md.I complete | 0301 |
| Md.III | VEX Lens, Excititor | Md.II complete | 0302 |
| Md.IV | Policy, Risk | Md.II complete | 0303 |
| Md.V | Scheduler, TaskRunner | Md.IV complete | 0304 |
| Md.VI | Notify, Telemetry | Md.V complete | 0305 |
| Md.VII | CLI, Web | Md.VI complete | 0306 |
| Md.VIII | AirGap, Mirror | Md.VII complete | 0307 |
| Md.IX | Zastava, Signals | Md.VIII complete | 0308 |
| Md.X | Integration, E2E | All above | 0309 |
Parallelism Rules
Within each phase, dossiers MAY be worked in parallel if:
- No cross-dependencies within the phase
- Shared components are stable
- Different owners/guilds assigned
Impact
- Tasks unblocked: ~10
- Sprint files affected: SPRINT_0300, SPRINT_0301, SPRINT_0302
Reversibility
To change sequencing:
- Propose new order in
docs/operations/process/dossier-sequencing.md - Get Docs Guild sign-off
- Update all affected SPRINT_03xx files