feat(crypto): Complete Phase 2 - Configuration-driven crypto architecture with 100% compliance
## Summary
This commit completes Phase 2 of the configuration-driven crypto architecture, achieving
100% crypto compliance by eliminating all hardcoded cryptographic implementations.
## Key Changes
### Phase 1: Plugin Loader Infrastructure
- **Plugin Discovery System**: Created StellaOps.Cryptography.PluginLoader with manifest-based loading
- **Configuration Model**: Added CryptoPluginConfiguration with regional profiles support
- **Dependency Injection**: Extended DI to support plugin-based crypto provider registration
- **Regional Configs**: Created appsettings.crypto.{international,russia,eu,china}.yaml
- **CI Workflow**: Added .gitea/workflows/crypto-compliance.yml for audit enforcement
### Phase 2: Code Refactoring
- **API Extension**: Added ICryptoProvider.CreateEphemeralVerifier for verification-only scenarios
- **Plugin Implementation**: Created OfflineVerificationCryptoProvider with ephemeral verifier support
- Supports ES256/384/512, RS256/384/512, PS256/384/512
- SubjectPublicKeyInfo (SPKI) public key format
- **100% Compliance**: Refactored DsseVerifier to remove all BouncyCastle cryptographic usage
- **Unit Tests**: Created OfflineVerificationProviderTests with 39 passing tests
- **Documentation**: Created comprehensive security guide at docs/security/offline-verification-crypto-provider.md
- **Audit Infrastructure**: Created scripts/audit-crypto-usage.ps1 for static analysis
### Testing Infrastructure (TestKit)
- **Determinism Gate**: Created DeterminismGate for reproducibility validation
- **Test Fixtures**: Added PostgresFixture and ValkeyFixture using Testcontainers
- **Traits System**: Implemented test lane attributes for parallel CI execution
- **JSON Assertions**: Added CanonicalJsonAssert for deterministic JSON comparisons
- **Test Lanes**: Created test-lanes.yml workflow for parallel test execution
### Documentation
- **Architecture**: Created CRYPTO_CONFIGURATION_DRIVEN_ARCHITECTURE.md master plan
- **Sprint Tracking**: Created SPRINT_1000_0007_0002_crypto_refactoring.md (COMPLETE)
- **API Documentation**: Updated docs2/cli/crypto-plugins.md and crypto.md
- **Testing Strategy**: Created testing strategy documents in docs/implplan/SPRINT_5100_0007_*
## Compliance & Testing
- ✅ Zero direct System.Security.Cryptography usage in production code
- ✅ All crypto operations go through ICryptoProvider abstraction
- ✅ 39/39 unit tests passing for OfflineVerificationCryptoProvider
- ✅ Build successful (AirGap, Crypto plugin, DI infrastructure)
- ✅ Audit script validates crypto boundaries
## Files Modified
**Core Crypto Infrastructure:**
- src/__Libraries/StellaOps.Cryptography/CryptoProvider.cs (API extension)
- src/__Libraries/StellaOps.Cryptography/CryptoSigningKey.cs (verification-only constructor)
- src/__Libraries/StellaOps.Cryptography/EcdsaSigner.cs (fixed ephemeral verifier)
**Plugin Implementation:**
- src/__Libraries/StellaOps.Cryptography.Plugin.OfflineVerification/ (new)
- src/__Libraries/StellaOps.Cryptography.PluginLoader/ (new)
**Production Code Refactoring:**
- src/AirGap/StellaOps.AirGap.Importer/Validation/DsseVerifier.cs (100% compliant)
**Tests:**
- src/__Libraries/__Tests/StellaOps.Cryptography.Plugin.OfflineVerification.Tests/ (new, 39 tests)
- src/__Libraries/__Tests/StellaOps.Cryptography.PluginLoader.Tests/ (new)
**Configuration:**
- etc/crypto-plugins-manifest.json (plugin registry)
- etc/appsettings.crypto.*.yaml (regional profiles)
**Documentation:**
- docs/security/offline-verification-crypto-provider.md (600+ lines)
- docs/implplan/CRYPTO_CONFIGURATION_DRIVEN_ARCHITECTURE.md (master plan)
- docs/implplan/SPRINT_1000_0007_0002_crypto_refactoring.md (Phase 2 complete)
## Next Steps
Phase 3: Docker & CI/CD Integration
- Create multi-stage Dockerfiles with all plugins
- Build regional Docker Compose files
- Implement runtime configuration selection
- Add deployment validation scripts
🤖 Generated with [Claude Code](https://claude.com/claude-code)
Co-Authored-By: Claude Sonnet 4.5 <noreply@anthropic.com>
This commit is contained in:
419
docs/testing/TESTING_MASTER_PLAN.md
Normal file
419
docs/testing/TESTING_MASTER_PLAN.md
Normal file
@@ -0,0 +1,419 @@
|
||||
# StellaOps Testing Strategy Master Plan (2026 H1)
|
||||
|
||||
> **Executive Summary:** Comprehensive 14-week testing initiative to establish model-driven test coverage across 15 modules, implement 6 foundation epics, and achieve 30%+ code coverage increase platform-wide.
|
||||
|
||||
---
|
||||
|
||||
## Document Control
|
||||
|
||||
| Attribute | Value |
|
||||
|-----------|-------|
|
||||
| **Program Name** | Testing Strategy Implementation 2026 H1 |
|
||||
| **Program ID** | SPRINT-5100 |
|
||||
| **Owner** | Project Management |
|
||||
| **Status** | PLANNING |
|
||||
| **Start Date** | 2026-01-06 (Week 1) |
|
||||
| **Target End Date** | 2026-04-14 (Week 14) |
|
||||
| **Budget** | TBD (resource model below) |
|
||||
| **Last Updated** | 2025-12-23 |
|
||||
|
||||
---
|
||||
|
||||
## Table of Contents
|
||||
1. [Program Objectives](#program-objectives)
|
||||
2. [Scope & Deliverables](#scope--deliverables)
|
||||
3. [Timeline & Phases](#timeline--phases)
|
||||
4. [Resource Model](#resource-model)
|
||||
5. [Risk Register](#risk-register)
|
||||
6. [Success Metrics](#success-metrics)
|
||||
7. [Governance](#governance)
|
||||
8. [Communication Plan](#communication-plan)
|
||||
|
||||
---
|
||||
|
||||
## Program Objectives
|
||||
|
||||
### Primary Objectives
|
||||
|
||||
1. **Establish Model-Driven Testing:** Implement 9 test models (L0, S1, T1, C1, W1, WK1, AN1, CLI1, PERF) across 15 modules
|
||||
2. **Increase Code Coverage:** Achieve ≥30% code coverage increase from baseline (current ~40% → target 70%+)
|
||||
3. **Enforce Quality Gates:** Implement determinism, architecture, and module-specific quality gates
|
||||
4. **Build Test Infrastructure:** Deliver 6 foundation epics (TestKit, Determinism, Storage, Connectors, WebService, Architecture)
|
||||
5. **Enable CI/CD Confidence:** Establish PR-gating and merge-gating test lanes
|
||||
|
||||
### Secondary Objectives
|
||||
|
||||
1. **Reduce Test Flakiness:** Achieve 100% deterministic test pass rate (eliminate timing-based failures)
|
||||
2. **Improve Developer Experience:** Standardize test patterns, reduce test authoring friction
|
||||
3. **Establish Parity Monitoring:** Continuous validation against competitor tools (Syft, Grype, Trivy, Anchore)
|
||||
4. **Document Test Strategy:** Create comprehensive testing guides and playbooks
|
||||
|
||||
---
|
||||
|
||||
## Scope & Deliverables
|
||||
|
||||
### In-Scope
|
||||
|
||||
#### Foundation Epics (Batch 5100.0007, 90 tasks)
|
||||
| Sprint ID | Epic | Deliverables |
|
||||
|-----------|------|--------------|
|
||||
| 5100.0007.0001 | Master Testing Strategy | Strategy docs, test runner scripts, trait standardization, Epic sprint creation |
|
||||
| 5100.0007.0002 | TestKit Foundations | DeterministicTime, DeterministicRandom, CanonicalJsonAssert, SnapshotAssert, PostgresFixture, ValkeyFixture, OtelCapture, HttpFixtureServer |
|
||||
| 5100.0007.0003 | Determinism Gate | Determinism manifest format, expanded integration tests, CI artifact storage, drift detection |
|
||||
| 5100.0007.0004 | Storage Harness | PostgresFixture (Testcontainers), ValkeyFixture, automatic migrations, schema isolation |
|
||||
| 5100.0007.0005 | Connector Fixtures | Fixture discipline, FixtureUpdater tool, pilot adoption in Concelier.Connector.NVD |
|
||||
| 5100.0007.0006 | WebService Contract | WebServiceFixture<TProgram>, contract test pattern, pilot adoption in Scanner.WebService |
|
||||
| 5100.0007.0007 | Architecture Tests | NetArchTest.Rules, lattice placement enforcement, PR-gating architecture tests |
|
||||
|
||||
#### Module Test Implementations (Batch 5100.0009, 185 tasks)
|
||||
| Sprint ID | Module | Test Models | Deliverables |
|
||||
|-----------|--------|-------------|--------------|
|
||||
| 5100.0009.0001 | Scanner | L0, AN1, S1, T1, W1, WK1, PERF | 25 tasks: property tests, SBOM/reachability/verdict snapshots, determinism, WebService contract, Worker e2e, perf smoke |
|
||||
| 5100.0009.0002 | Concelier | C1, L0, S1, W1, AN1 | 18 tasks: connector fixtures (NVD/OSV/GHSA/CSAF), merge property tests, WebService contract, architecture enforcement |
|
||||
| 5100.0009.0003 | Excititor | C1, L0, S1, W1, WK1 | 21 tasks: connector fixtures (CSAF/OpenVEX), format export snapshots, preserve-prune tests, Worker e2e, architecture enforcement |
|
||||
| 5100.0009.0004 | Policy | L0, S1, W1 | 15 tasks: policy engine property tests, DSL roundtrip tests, verdict snapshots, unknown budget enforcement |
|
||||
| 5100.0009.0005 | Authority | L0, W1, C1 | 17 tasks: auth logic tests, connector fixtures (OIDC/SAML/LDAP), WebService contract, sign/verify integration |
|
||||
| 5100.0009.0006 | Signer | L0, W1, C1 | 17 tasks: canonical payload tests, crypto plugin tests (BouncyCastle/CryptoPro/eIDAS/SimRemote), WebService contract |
|
||||
| 5100.0009.0007 | Attestor | L0, W1 | 14 tasks: DSSE envelope tests, Rekor integration tests, attestation statement snapshots, WebService contract |
|
||||
| 5100.0009.0008 | Scheduler | L0, S1, W1, WK1 | 14 tasks: scheduling invariant property tests, storage idempotency, WebService contract, Worker e2e |
|
||||
| 5100.0009.0009 | Notify | L0, C1, S1, W1, WK1 | 18 tasks: connector fixtures (email/Slack/Teams/webhook), WebService contract, Worker e2e |
|
||||
| 5100.0009.0010 | CLI | CLI1 | 13 tasks: exit code tests, golden output tests, determinism tests |
|
||||
| 5100.0009.0011 | UI | W1 | 13 tasks: API contract tests, E2E smoke tests, accessibility tests |
|
||||
|
||||
#### Infrastructure Test Implementations (Batch 5100.0010, 62 tasks)
|
||||
| Sprint ID | Module Family | Deliverables |
|
||||
|-----------|---------------|--------------|
|
||||
| 5100.0010.0001 | EvidenceLocker + Findings + Replay | Immutability tests, ledger determinism, replay token security, WebService contract |
|
||||
| 5100.0010.0002 | Graph + TimelineIndexer | Graph construction/traversal tests, indexer e2e, query determinism, WebService contract |
|
||||
| 5100.0010.0003 | Router + Messaging | Transport compliance suite (in-memory/TCP/TLS/Valkey/RabbitMQ), routing determinism, fuzz tests |
|
||||
| 5100.0010.0004 | AirGap | Bundle export/import determinism, policy analyzer tests, WebService contract, CLI tool tests |
|
||||
|
||||
#### Quality Gates (Batch 5100.0008, 11 tasks)
|
||||
| Sprint ID | Purpose | Deliverables |
|
||||
|-----------|---------|--------------|
|
||||
| 5100.0008.0001 | Competitor Parity Testing | Parity test harness, fixture set (10-15 container images), comparison logic (SBOM/vuln/latency/errors), time-series storage, drift detection (>5% threshold) |
|
||||
|
||||
### Out-of-Scope
|
||||
|
||||
- ❌ **Performance optimization** (beyond PERF smoke tests for Scanner)
|
||||
- ❌ **UI/UX testing** (beyond W1 contract tests and E2E smoke tests)
|
||||
- ❌ **Load testing** (deferred to future sprint)
|
||||
- ❌ **Chaos engineering** (deferred to future sprint)
|
||||
- ❌ **Mobile/responsive testing** (not applicable - server-side platform)
|
||||
- ❌ **Penetration testing** (separate security initiative)
|
||||
|
||||
---
|
||||
|
||||
## Timeline & Phases
|
||||
|
||||
### Master Timeline (14 Weeks, 2026-01-06 to 2026-04-14)
|
||||
|
||||
```
|
||||
PHASE 1: FOUNDATION (Weeks 1-4)
|
||||
┌─────────────────────────────────────────────────────────────┐
|
||||
│ Week 1-2: Master Strategy (5100.0007.0001) │
|
||||
│ - Documentation sync │
|
||||
│ - Test runner scripts │
|
||||
│ - Trait standardization │
|
||||
│ - Epic sprint creation │
|
||||
│ │
|
||||
│ Week 3-4: TestKit Foundations (5100.0007.0002) ← CRITICAL │
|
||||
│ - DeterministicTime, DeterministicRandom │
|
||||
│ - CanonicalJsonAssert, SnapshotAssert │
|
||||
│ - PostgresFixture, ValkeyFixture, OtelCapture │
|
||||
└─────────────────────────────────────────────────────────────┘
|
||||
|
||||
PHASE 2: EPIC IMPLEMENTATION (Weeks 5-6)
|
||||
┌─────────────────────────────────────────────────────────────┐
|
||||
│ Week 5-6: 5 Epic Sprints (PARALLEL) │
|
||||
│ - 5100.0007.0003 (Determinism Gate) │
|
||||
│ - 5100.0007.0004 (Storage Harness) │
|
||||
│ - 5100.0007.0005 (Connector Fixtures) │
|
||||
│ - 5100.0007.0006 (WebService Contract) │
|
||||
│ - 5100.0007.0007 (Architecture Tests) │
|
||||
└─────────────────────────────────────────────────────────────┘
|
||||
|
||||
PHASE 3: MODULE TESTS - TIER 1 (Weeks 7-8)
|
||||
┌─────────────────────────────────────────────────────────────┐
|
||||
│ Week 7-8: 6 Module Sprints (PARALLEL) │
|
||||
│ - Scanner, Concelier, Excititor (core platform) │
|
||||
│ - Policy, Authority, Signer (security/compliance) │
|
||||
└─────────────────────────────────────────────────────────────┘
|
||||
|
||||
PHASE 4: MODULE TESTS - TIER 2 (Weeks 9-10)
|
||||
┌─────────────────────────────────────────────────────────────┐
|
||||
│ Week 9-10: 5 Module Sprints (PARALLEL) │
|
||||
│ - Attestor, Scheduler, Notify (platform services) │
|
||||
│ - CLI, UI (client interfaces) │
|
||||
└─────────────────────────────────────────────────────────────┘
|
||||
|
||||
PHASE 5: INFRASTRUCTURE TESTS (Weeks 11-14)
|
||||
┌─────────────────────────────────────────────────────────────┐
|
||||
│ Week 11-14: 4 Infrastructure Sprints (PARALLEL) │
|
||||
│ - EvidenceLocker, Graph, Router/Messaging, AirGap │
|
||||
└─────────────────────────────────────────────────────────────┘
|
||||
|
||||
ONGOING: QUALITY GATES (Weeks 3-14+)
|
||||
┌─────────────────────────────────────────────────────────────┐
|
||||
│ Week 3: Competitor Parity harness setup │
|
||||
│ Week 4+: Nightly/weekly parity tests │
|
||||
└─────────────────────────────────────────────────────────────┘
|
||||
```
|
||||
|
||||
### Critical Path (14 Weeks)
|
||||
|
||||
**Week 1-2:** Master Strategy → **Week 3-4:** TestKit ← **BOTTLENECK** → **Week 5-6:** Epic Implementation → **Week 7-10:** Module Tests → **Week 11-14:** Infrastructure Tests
|
||||
|
||||
**Critical Path Risks:**
|
||||
- TestKit delay → ALL downstream sprints blocked (+2-4 weeks)
|
||||
- Storage harness delay → 10 sprints blocked (+2-3 weeks)
|
||||
|
||||
### Milestones
|
||||
|
||||
| Milestone | Week | Deliverables | Sign-Off Criteria |
|
||||
|-----------|------|--------------|-------------------|
|
||||
| **M1: Foundation Ready** | Week 4 | TestKit operational | DeterministicTime, SnapshotAssert, PostgresFixture, OtelCapture available; pilot adoption in 2+ modules |
|
||||
| **M2: Epic Complete** | Week 6 | All 6 foundation epics complete | Determinism gate in CI; Storage harness operational; WebService contract tests in Scanner; Architecture tests PR-gating |
|
||||
| **M3: Core Modules Tested** | Week 8 | Scanner, Concelier, Excititor, Policy, Authority, Signer complete | Code coverage increase ≥30%; quality gates passing |
|
||||
| **M4: All Modules Tested** | Week 10 | All 11 module test sprints complete | All module-specific quality gates passing |
|
||||
| **M5: Program Complete** | Week 14 | All infrastructure tests complete; program retrospective | All sprints signed off; final metrics review |
|
||||
|
||||
---
|
||||
|
||||
## Resource Model
|
||||
|
||||
### Guild Allocation
|
||||
|
||||
| Guild | Assigned Sprints | Peak Staffing (Weeks 7-10) | Avg Sprint Ownership |
|
||||
|-------|------------------|----------------------------|----------------------|
|
||||
| **Platform Guild** | TestKit, Storage, Architecture, EvidenceLocker, Graph, Router | 10 engineers | 6 sprints |
|
||||
| **Scanner Guild** | Scanner | 3 engineers | 1 sprint |
|
||||
| **Concelier Guild** | Concelier | 2 engineers | 1 sprint |
|
||||
| **Excititor Guild** | Excititor | 2 engineers | 1 sprint |
|
||||
| **Policy Guild** | Policy, AirGap (analyzers) | 2-4 engineers | 2 sprints |
|
||||
| **Authority Guild** | Authority | 2 engineers | 1 sprint |
|
||||
| **Crypto Guild** | Signer, Attestor | 4 engineers | 2 sprints |
|
||||
| **Scheduler Guild** | Scheduler | 2 engineers | 1 sprint |
|
||||
| **Notify Guild** | Notify | 2 engineers | 1 sprint |
|
||||
| **CLI Guild** | CLI | 1 engineer | 1 sprint |
|
||||
| **UI Guild** | UI | 2 engineers | 1 sprint |
|
||||
| **AirGap Guild** | AirGap (core) | 2 engineers | 1 sprint |
|
||||
| **QA Guild** | Competitor Parity | 2 engineers | 1 sprint |
|
||||
|
||||
### Staffing Profile
|
||||
|
||||
**Peak Staffing (Weeks 7-10):** 22-26 engineers
|
||||
**Average Staffing (Weeks 1-14):** 12-16 engineers
|
||||
**Critical Path Sprints (TestKit, Storage):** 3-4 senior engineers each
|
||||
|
||||
### Resource Constraints
|
||||
|
||||
| Constraint | Impact | Mitigation |
|
||||
|------------|--------|------------|
|
||||
| Platform Guild oversubscribed (10 engineers, 6 sprints) | Burnout, delays | Stagger Epic sprints (Storage Week 5, Connectors Week 6); hire contractors for Weeks 5-10 |
|
||||
| Senior engineers limited (5-6 available) | TestKit/Storage quality risk | Assign 2 senior engineers to TestKit (critical path); 1 senior to Storage; rotate for reviews |
|
||||
| UI Guild availability (Angular expertise scarce) | UI sprint delayed | Start UI sprint Week 10 (after Tier 1/2 modules); hire Angular contractor if needed |
|
||||
|
||||
---
|
||||
|
||||
## Risk Register
|
||||
|
||||
### High-Impact Risks (Severity: CRITICAL)
|
||||
|
||||
| ID | Risk | Probability | Impact | Mitigation | Owner | Status |
|
||||
|----|------|-------------|--------|------------|-------|--------|
|
||||
| R1 | TestKit delayed by 2+ weeks | MEDIUM | Blocks ALL 15 module/infra sprints; +4-6 weeks program delay | Staff with 2 senior engineers; daily standups; incremental releases (partial TestKit unblocks some modules) | Platform Guild | OPEN |
|
||||
| R2 | Storage harness (Testcontainers) incompatible with .NET 10 | LOW | Blocks 10 sprints; +3-4 weeks delay | Validate Testcontainers compatibility Week 1; fallback to manual Postgres setup | Platform Guild | OPEN |
|
||||
| R3 | Determinism tests fail due to non-deterministic crypto signatures | MEDIUM | Scanner, Signer, Attestor blocked; compliance issues | Focus determinism tests on payload hash (not signature bytes); document non-deterministic algorithms | Crypto Guild | OPEN |
|
||||
| R4 | Concurrent module tests overwhelm CI infrastructure | HIGH | Test suite timeout, flaky tests, developer friction | Stagger module test starts (Tier 1 Week 7-8, Tier 2 Week 9-10); use dedicated CI runners; implement CI parallelization | Platform Guild | OPEN |
|
||||
|
||||
### Medium-Impact Risks
|
||||
|
||||
| ID | Risk | Probability | Impact | Mitigation | Owner | Status |
|
||||
|----|------|-------------|--------|------------|-------|--------|
|
||||
| R5 | Attestor-Signer circular dependency blocks integration tests | MEDIUM | Integration tests delayed 1-2 weeks | Signer uses mock attestation initially; coordinate integration in Week 9 | Crypto Guild | OPEN |
|
||||
| R6 | Upstream schema drift (NVD, OSV) breaks connector fixtures | MEDIUM | Connector tests fail; manual fixture regeneration required | FixtureUpdater tool automates regeneration; weekly live smoke tests detect drift early | Concelier Guild | OPEN |
|
||||
| R7 | WebService contract tests too brittle (fail on every API change) | MEDIUM | Developer friction, contract tests disabled | Version APIs explicitly; allow non-breaking changes; review contract test strategy Week 6 | Platform Guild | OPEN |
|
||||
|
||||
### Low-Impact Risks
|
||||
|
||||
| ID | Risk | Probability | Impact | Mitigation | Owner | Status |
|
||||
|----|------|-------------|--------|------------|-------|--------|
|
||||
| R8 | Property test generation too slow (FsCheck iterations high) | LOW | Test suite timeout | Limit property test iterations (default 100 → 50); profile and optimize generators | Scanner Guild | OPEN |
|
||||
| R9 | Architecture tests false positive (allowlist too restrictive) | LOW | Valid code blocked | Review architecture rules Week 5; explicit allowlist for test projects, benchmarks | Platform Guild | OPEN |
|
||||
| R10 | Competitor parity tests require paid Trivy/Anchore licenses | LOW | Parity testing incomplete | Use Trivy free tier; defer Anchore to future sprint; focus on Syft/Grype (OSS) | QA Guild | OPEN |
|
||||
|
||||
### Risk Burn-Down Plan
|
||||
|
||||
**Week 1:** Validate Testcontainers .NET 10 compatibility (R2)
|
||||
**Week 2:** TestKit API design review (R1)
|
||||
**Week 4:** Determinism test strategy review (R3)
|
||||
**Week 6:** CI infrastructure capacity review (R4)
|
||||
**Week 8:** Signer-Attestor integration coordination (R5)
|
||||
|
||||
---
|
||||
|
||||
## Success Metrics
|
||||
|
||||
### Quantitative Metrics
|
||||
|
||||
| Metric | Baseline | Target | Measurement Method | Tracked By |
|
||||
|--------|----------|--------|-------------------|------------|
|
||||
| **Code Coverage** | ~40% | ≥70% | `dotnet test --collect:"XPlat Code Coverage"` | Weekly (Fridays) |
|
||||
| **Test Count** | ~200 tests | ≥500 tests | Test suite execution count | Weekly |
|
||||
| **Determinism Pass Rate** | N/A (not tracked) | 100% (no flaky tests) | Determinism gate CI job | Daily (CI) |
|
||||
| **Contract Test Coverage** | 0 WebServices | 13 WebServices (100%) | Contract lane CI job | Weekly |
|
||||
| **Architecture Violations** | Unknown | 0 violations | Architecture test failures | Daily (CI, PR gate) |
|
||||
| **Sprint On-Time Completion** | N/A | ≥80% | Tasks complete by wave deadline | Weekly |
|
||||
|
||||
### Qualitative Metrics
|
||||
|
||||
| Metric | Success Criteria | Measurement Method | Tracked By |
|
||||
|--------|------------------|-------------------|------------|
|
||||
| **Developer Experience** | ≥80% of developers rate test authoring as "easy" or "very easy" | Post-sprint developer survey (Week 14) | Project Manager |
|
||||
| **Test Maintainability** | ≥75% of test failures are due to actual bugs (not test brittleness) | Monthly test failure classification | QA Guild |
|
||||
| **Integration Confidence** | ≥90% of PRs pass CI on first attempt (no test fixes required) | CI metrics (PR pass rate) | Platform Guild |
|
||||
|
||||
### Program Success Criteria
|
||||
|
||||
✅ **Program Successful If:**
|
||||
- All 22 sprints signed off (5100.0007.* + 5100.0008.0001 + 5100.0009.* + 5100.0010.*)
|
||||
- Code coverage ≥70% platform-wide
|
||||
- Determinism tests passing 100% in CI (no flaky tests)
|
||||
- Contract tests enforced for all 13 WebServices
|
||||
- Architecture tests PR-gating (lattice boundary violations blocked)
|
||||
|
||||
❌ **Program Failed If:**
|
||||
- <18 sprints signed off (<80% completion)
|
||||
- Code coverage increase <20% (baseline ~40% → <60%)
|
||||
- Critical quality gates missing (Determinism, Architecture, Contract)
|
||||
- TestKit not operational (blocking all module tests)
|
||||
|
||||
---
|
||||
|
||||
## Governance
|
||||
|
||||
### Steering Committee
|
||||
|
||||
| Role | Name | Responsibility |
|
||||
|------|------|----------------|
|
||||
| **Program Sponsor** | CTO | Final escalation; budget approval |
|
||||
| **Program Manager** | Project Management | Overall program coordination; risk management |
|
||||
| **Technical Lead** | Platform Guild Lead | Architecture decisions; technical escalation |
|
||||
| **QA Lead** | QA Guild Lead | Quality gate oversight; test strategy validation |
|
||||
|
||||
### Decision-Making Authority
|
||||
|
||||
| Decision Type | Authority | Escalation Path |
|
||||
|---------------|-----------|----------------|
|
||||
| **Sprint scope changes** | Sprint owner + Guild lead | Program Manager → Steering Committee |
|
||||
| **Architecture changes** | Platform Guild Lead | Steering Committee |
|
||||
| **Resource allocation** | Program Manager | CTO (if >10% budget impact) |
|
||||
| **Schedule changes (>1 week)** | Program Manager | Steering Committee |
|
||||
| **Risk acceptance** | Program Manager | Steering Committee (for HIGH/CRITICAL risks) |
|
||||
|
||||
### Status Reporting
|
||||
|
||||
**Weekly Status Report (Fridays):**
|
||||
- Sprint completion status (% tasks complete)
|
||||
- Blockers and risks (RED/YELLOW/GREEN)
|
||||
- Resource allocation (current vs. planned)
|
||||
- Next week preview
|
||||
|
||||
**Monthly Executive Summary:**
|
||||
- Program health (on-track / at-risk / off-track)
|
||||
- Milestone completion (M1-M5)
|
||||
- Budget vs. actuals
|
||||
- Key risks and mitigations
|
||||
|
||||
### Change Control
|
||||
|
||||
**Change Request Process:**
|
||||
1. **Requester submits change request** (scope, schedule, or resource change)
|
||||
2. **Program Manager reviews** (impact analysis: cost, schedule, quality)
|
||||
3. **Steering Committee approves/rejects** (for changes >1 week or >10% budget)
|
||||
4. **Program Manager updates plan** (timeline, resource model, risk register)
|
||||
|
||||
---
|
||||
|
||||
## Communication Plan
|
||||
|
||||
### Stakeholders
|
||||
|
||||
| Stakeholder Group | Interest | Communication Frequency | Method |
|
||||
|-------------------|----------|------------------------|--------|
|
||||
| **Engineering Teams (Guilds)** | Sprint execution, dependencies | Daily/Weekly | Slack #testing-strategy, guild standups |
|
||||
| **Guild Leads** | Sprint status, blockers | Weekly | Friday status sync (30 min) |
|
||||
| **Product Management** | Quality gates, feature readiness | Bi-weekly | Sprint demos, monthly exec summary |
|
||||
| **CTO / Executives** | Program health, budget | Monthly | Executive summary (email) |
|
||||
|
||||
### Meetings
|
||||
|
||||
#### Weekly Sync (Every Friday, 30 min)
|
||||
**Attendees:** All active sprint owners + program manager
|
||||
**Agenda:**
|
||||
1. Sprint status updates (green/yellow/red) (15 min)
|
||||
2. Blocker escalation (10 min)
|
||||
3. Next week preview (5 min)
|
||||
|
||||
#### Monthly Steering Committee (First Monday, 60 min)
|
||||
**Attendees:** Steering Committee (CTO, Program Manager, Platform Guild Lead, QA Lead)
|
||||
**Agenda:**
|
||||
1. Program health review (on-track / at-risk / off-track) (20 min)
|
||||
2. Milestone completion (M1-M5) (15 min)
|
||||
3. Budget vs. actuals (10 min)
|
||||
4. Risk review (top 3 risks) (10 min)
|
||||
5. Decisions required (5 min)
|
||||
|
||||
#### Retrospective (Week 14, 90 min)
|
||||
**Attendees:** All guild leads + program manager + steering committee
|
||||
**Agenda:**
|
||||
1. Program retrospective (what went well, what didn't, lessons learned) (60 min)
|
||||
2. Metrics review (code coverage, test count, determinism, etc.) (20 min)
|
||||
3. Future improvements (next testing initiatives) (10 min)
|
||||
|
||||
---
|
||||
|
||||
## Appendices
|
||||
|
||||
### Appendix A: Sprint Inventory
|
||||
|
||||
**Total Sprints:** 22
|
||||
- Foundation Epics: 7 (5100.0007.0001-0007)
|
||||
- Quality Gates: 1 (5100.0008.0001)
|
||||
- Module Tests: 11 (5100.0009.0001-0011)
|
||||
- Infrastructure Tests: 4 (5100.0010.0001-0004)
|
||||
|
||||
**Total Tasks:** ~370 tasks
|
||||
**Total Estimated Effort:** ~450 engineer-days (assuming avg 1.2 days/task)
|
||||
|
||||
### Appendix B: Reference Documents
|
||||
|
||||
1. **Advisory:** `docs/product-advisories/22-Dec-2026 - Better testing strategy.md`
|
||||
2. **Test Catalog:** `docs/testing/TEST_CATALOG.yml`
|
||||
3. **Test Models:** `docs/testing/testing-strategy-models.md`
|
||||
4. **Dependency Graph:** `docs/testing/SPRINT_DEPENDENCY_GRAPH.md`
|
||||
5. **Coverage Matrix:** `docs/testing/TEST_COVERAGE_MATRIX.md`
|
||||
6. **Execution Playbook:** `docs/testing/SPRINT_EXECUTION_PLAYBOOK.md`
|
||||
|
||||
### Appendix C: Budget Estimate (Preliminary)
|
||||
|
||||
**Assumptions:**
|
||||
- Average engineer cost: $150/hour (fully loaded)
|
||||
- Average sprint duration: 80 hours (2 weeks × 40 hours)
|
||||
- Peak staffing: 22 engineers (Weeks 7-10)
|
||||
|
||||
**Budget Estimate:**
|
||||
- Foundation Phase (Weeks 1-6): 12 engineers × 240 hours × $150 = $432,000
|
||||
- Module Tests Phase (Weeks 7-10): 22 engineers × 160 hours × $150 = $528,000
|
||||
- Infrastructure Phase (Weeks 11-14): 8 engineers × 160 hours × $150 = $192,000
|
||||
- **Total Estimated Cost:** $1,152,000
|
||||
|
||||
**Note:** Final budget requires approval from CTO/Finance. Contractor costs may reduce total if used strategically for peak staffing (Weeks 7-10).
|
||||
|
||||
---
|
||||
|
||||
**Prepared by:** Project Management
|
||||
**Approval Required From:** Steering Committee (CTO, Program Manager, Platform Guild Lead, QA Lead)
|
||||
**Date:** 2025-12-23
|
||||
**Next Review:** 2026-01-06 (Week 1 kickoff)
|
||||