# Lineage UI Sprints - Status Assessment
|
||||
|
||||
**Date:** 2025-12-29
|
||||
**Assessment:** Comprehensive review of all pending UI sprints
|
||||
|
||||
---
|
||||
|
||||
## Executive Summary
|
||||
|
||||
The StellaOps lineage UI has **36 component files** already implemented with ~70-80% functionality complete. Most components exist but need:
|
||||
- ✅ Final polish (styles, dark mode, accessibility)
|
||||
- ✅ API wiring verification (some already done)
|
||||
- ⚠️ Missing: A few specific components (Node Diff Table, Pinned Explanations UI)
|
||||
|
||||
**Quick Win Opportunity:** Complete the remaining 20-30% to deliver a fully functional lineage experience.
|
||||
|
||||
---
|
||||
|
||||
## Sprint-by-Sprint Status
|
||||
|
||||
### ✅ SPRINT_20251229_001_003_FE: CGS Integration (Partially Done)
|
||||
|
||||
**Status:** 60% Complete
|
||||
**Location:** `src/app/features/lineage/components/lineage-graph/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| LG-001: Update graph component | ✅ DONE | Component exists with CGS hash display |
|
||||
| LG-002: Add CGS hash display | ✅ DONE | Visible in node badges |
|
||||
| LG-003: Add replay button | ⚠️ PARTIAL | Button exists, needs backend wiring |
|
||||
| LG-004: Wire to replay API | ❌ TODO | API call not implemented |
|
||||
| LG-005: Add loading/error states | ✅ DONE | States exist |
|
||||
| LG-006: Unit tests | ❌ DEFERRED | Tests not written |
|
||||
|
||||
**Files:** `lineage-graph.component.ts`, `replay-hash-display.component.ts` exist
|
||||
|
||||
---
|
||||
|
||||
### ✅ SPRINT_20251229_001_004_FE: Proof Studio (Not Started)
|
||||
|
||||
**Status:** 0% Complete
|
||||
**Expected Location:** `src/app/features/lineage/components/proof-studio/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| PS-001: Create ProofStudioComponent | ❌ TODO | Component doesn't exist |
|
||||
| PS-002: Create ProofChainViewer | ❌ TODO | Not implemented |
|
||||
| PS-003: Create FactDisplay | ❌ TODO | Not implemented |
|
||||
| PS-004: Wire to ProofTrace API | ❌ TODO | Service not created |
|
||||
| PS-005: Add export functionality | ❌ TODO | Not implemented |
|
||||
| PS-006: Unit tests | ❌ DEFERRED | N/A |
|
||||
|
||||
**Priority:** P1 (High value for debugging)
|
||||
**Effort:** 3-4 days
|
||||
**Recommendation:** Implement after higher priority items
|
||||
|
||||
---
|
||||
|
||||
### ✅ SPRINT_20251229_001_005_FE: Explainer Timeline (70% Done)
|
||||
|
||||
**Status:** 70% Complete
|
||||
**Location:** `src/app/features/lineage/components/explainer-timeline/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| ET-001: Create component shell | ✅ DONE | `explainer-timeline.component.ts` |
|
||||
| ET-002: Design step data model | ✅ DONE | `models/explainer.models.ts` |
|
||||
| ET-003: Implement timeline layout | ✅ DONE | Vertical timeline with connectors |
|
||||
| ET-004: Implement step component | ✅ DONE | `explainer-step.component.ts` |
|
||||
| ET-005: Add expansion animation | ✅ DONE | @angular/animations used |
|
||||
| ET-006: Wire to ProofTrace API | ✅ DONE | Service integration ready |
|
||||
| ET-007: Confidence indicators | ⚠️ PARTIAL | Need visual polish |
|
||||
| ET-008: Copy-to-clipboard | ⚠️ PARTIAL | Button exists, needs implementation |
|
||||
| ET-009: Dark mode styling | ❌ TODO | SCSS not fully implemented |
|
||||
| ET-010: Accessibility | ❌ TODO | ARIA attributes missing |
|
||||
| ET-011: Unit tests | ❌ DEFERRED | Tests not written |
|
||||
| ET-012: Hover card integration | ❌ TODO | Not wired |
|
||||
|
||||
**Files:** 3 TS files, 2 HTML templates exist
|
||||
**Missing:** Complete SCSS, copy logic, a11y attributes
|
||||
|
||||
**Priority:** P0 (Critical UX feature)
|
||||
**Remaining Effort:** 1-2 days
|
||||
**Recommendation:** Complete immediately
|
||||
|
||||
---
|
||||
|
||||
### ❌ SPRINT_20251229_001_006_FE: Node Diff Table (Not Started)
|
||||
|
||||
**Status:** 0% Complete
|
||||
**Expected Location:** `src/app/features/lineage/components/node-diff-table/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| DT-001 to DT-011 | ❌ ALL TODO | Component doesn't exist |
|
||||
|
||||
**Note:** Existing `lineage-component-diff.component.ts` may provide similar functionality
|
||||
**Priority:** P0 (Core comparison feature)
|
||||
**Effort:** 3-4 days
|
||||
**Recommendation:** High priority, needed for diff workflows
|
||||
|
||||
---
|
||||
|
||||
### ⚠️ SPRINT_20251229_001_007_FE: Pinned Explanations (Not Started)
|
||||
|
||||
**Status:** 0% Complete
|
||||
**Expected Location:** `src/app/features/lineage/components/pinned-explanations/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| PE-001 to PE-010 | ❌ ALL TODO | Component doesn't exist |
|
||||
|
||||
**Priority:** P1 (Nice-to-have for tickets)
|
||||
**Effort:** 2-3 days
|
||||
**Recommendation:** Defer to post-MVP
|
||||
|
||||
---
|
||||
|
||||
### ⚠️ SPRINT_20251229_001_008_FE: Reachability Gate Diff (Partially Done)
|
||||
|
||||
**Status:** 30% Complete
|
||||
**Location:** `src/app/features/lineage/components/reachability-diff-view/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| RD-001: Enhance component | ⚠️ PARTIAL | `reachability-diff-view.component.ts` exists |
|
||||
| RD-002 to RD-009 | ❌ TODO | Gate visualization not complete |
|
||||
|
||||
**Existing:** Basic reachability diff display
|
||||
**Missing:** Gate chips, path comparison, confidence bar
|
||||
**Priority:** P1 (Security UX)
|
||||
**Effort:** 2-3 days
|
||||
**Recommendation:** Implement after P0 items
|
||||
|
||||
---
|
||||
|
||||
### ⚠️ SPRINT_20251229_001_009_FE: Audit Pack Export (Partially Done)
|
||||
|
||||
**Status:** 40% Complete
|
||||
**Location:** `src/app/features/lineage/components/lineage-export-dialog/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| AE-001: Enhance component | ⚠️ PARTIAL | `lineage-export-dialog.component.ts` exists |
|
||||
| AE-002 to AE-010 | ❌ PARTIAL | Basic export, needs format options + signing |
|
||||
|
||||
**Existing:** Basic export dialog
|
||||
**Missing:** Format selector, signing options, merkle display, progress tracking
|
||||
**Priority:** P2 (Compliance feature)
|
||||
**Effort:** 2-3 days
|
||||
**Recommendation:** Defer to iteration 2
|
||||
|
||||
---
|
||||
|
||||
### ✅ SPRINT_20251229_005_003_FE: Lineage UI API Wiring (80% Done)
|
||||
|
||||
**Status:** 80% Complete
|
||||
**Location:** `src/app/features/lineage/services/`
|
||||
|
||||
| Task | Status | Notes |
|
||||
|------|--------|-------|
|
||||
| UI-001: Update LineageService | ✅ DONE | Real API calls implemented |
|
||||
| UI-002: Wire GET /lineage | ✅ DONE | Graph loading works |
|
||||
| UI-003: Wire GET /lineage/diff | ✅ DONE | Diff API integrated |
|
||||
| UI-004: Hover card data loading | ✅ DONE | Observable streams working |
|
||||
| UI-005: Error states | ✅ DONE | Loading/error handling present |
|
||||
| UI-006: Export button | ⚠️ PARTIAL | UI exists, needs POST wiring |
|
||||
| UI-007: Caching layer | ✅ DONE | 5-minute TTL cache implemented |
|
||||
| UI-008: OpenAPI client | ❌ TODO | Manual client, not generated |
|
||||
| UI-009: E2E tests | ❌ DEFERRED | No E2E tests |
|
||||
|
||||
**Recommendation:** Verify endpoints match backend, add export API call
|
||||
|
||||
---
|
||||
|
||||
## Overall Statistics
|
||||
|
||||
| Metric | Count | Percentage |
|
||||
|--------|-------|------------|
|
||||
| **Total Sprint Tasks** | ~75 | 100% |
|
||||
| **Completed Tasks** | ~40 | 53% |
|
||||
| **Partially Done Tasks** | ~15 | 20% |
|
||||
| **Not Started Tasks** | ~20 | 27% |
|
||||
| **Deferred (Tests, Polish)** | ~15 | - |
|
||||
|
||||
---
|
||||
|
||||
## Critical Path to MVP
|
||||
|
||||
### Phase 1: P0 - Essential (3-5 days)
|
||||
|
||||
1. **Complete Explainer Timeline** (1-2 days)
|
||||
- Add missing SCSS styles
|
||||
- Implement copy-to-clipboard logic
|
||||
- Add dark mode support
|
||||
- Basic accessibility (ARIA labels)
|
||||
|
||||
2. **Build Node Diff Table** (2-3 days)
|
||||
- Create component from scratch
|
||||
- Wire to diff API
|
||||
- Add expand/collapse rows
|
||||
- Style with table/grid layout
|
||||
|
||||
3. **Verify API Wiring** (0.5 days)
|
||||
- Test all API endpoints
|
||||
- Add export POST call
|
||||
- Verify error handling
|
||||
|
||||
### Phase 2: P1 - High Value (4-6 days)
|
||||
|
||||
4. **Complete Reachability Gate Diff** (2-3 days)
|
||||
- Add gate chips
|
||||
- Add path comparison
|
||||
- Add confidence bar
|
||||
- Style and polish
|
||||
|
||||
5. **Build Proof Studio** (3-4 days)
|
||||
- Create proof chain viewer
|
||||
- Add fact display
|
||||
- Wire to API
|
||||
- Export functionality
|
||||
|
||||
### Phase 3: P2 - Nice-to-Have (3-4 days)
|
||||
|
||||
6. **Complete Audit Pack Export** (2-3 days)
|
||||
- Format selector
|
||||
- Signing options
|
||||
- Progress tracking
|
||||
- Merkle display
|
||||
|
||||
7. **Build Pinned Explanations** (2-3 days)
|
||||
- Pin/unpin UI
|
||||
- Local storage
|
||||
- Export to markdown
|
||||
|
||||
---
|
||||
|
||||
## Recommended Immediate Actions
|
||||
|
||||
### 1. Complete Explainer Timeline (Highest ROI)
|
||||
- **Why:** 70% done, high visibility feature
|
||||
- **Effort:** 1-2 days
|
||||
- **Files to modify:** Add SCSS, implement copy logic
|
||||
|
||||
### 2. Build Node Diff Table (Most Critical)
|
||||
- **Why:** Core comparison workflow, P0 priority
|
||||
- **Effort:** 2-3 days
|
||||
- **Files to create:** New component from scratch
|
||||
|
||||
### 3. Verify All API Endpoints (Risk Mitigation)
|
||||
- **Why:** Backend complete, UI may have stale endpoints
|
||||
- **Effort:** 0.5 days
|
||||
- **Files to modify:** Services only
|
||||
|
||||
---
|
||||
|
||||
## Files Inventory
|
||||
|
||||
### Existing Components (36 files)
|
||||
```
|
||||
src/app/features/lineage/components/
|
||||
├── attestation-links/
|
||||
├── compare-panel/
|
||||
├── export-dialog/ (partial)
|
||||
├── explainer-timeline/ (70% done)
|
||||
├── keyboard-shortcuts-help/
|
||||
├── lineage-compare/
|
||||
├── lineage-compare-panel/
|
||||
├── lineage-component-diff/
|
||||
├── lineage-controls/
|
||||
├── lineage-detail-panel/
|
||||
├── lineage-edge/
|
||||
├── lineage-export-buttons/
|
||||
├── lineage-export-dialog/ (partial)
|
||||
├── lineage-graph/ (main, mostly done)
|
||||
├── lineage-graph-container/
|
||||
├── lineage-hover-card/
|
||||
├── lineage-minimap/
|
||||
├── lineage-mobile-compare/
|
||||
├── lineage-node/
|
||||
├── lineage-provenance-chips/
|
||||
├── lineage-provenance-compare/
|
||||
├── lineage-sbom-diff/
|
||||
├── lineage-timeline-slider/
|
||||
├── lineage-vex-delta/
|
||||
├── lineage-vex-diff/
|
||||
├── lineage-why-safe-panel/
|
||||
├── reachability-diff-view/ (partial)
|
||||
├── replay-hash-display/
|
||||
├── timeline-slider/
|
||||
├── vex-diff-view/
|
||||
└── why-safe-panel/
|
||||
```
|
||||
|
||||
### Missing Components
|
||||
```
|
||||
src/app/features/lineage/components/
|
||||
├── node-diff-table/ (TODO - P0)
|
||||
├── proof-studio/ (TODO - P1)
|
||||
├── pinned-explanations/ (TODO - P1)
|
||||
└── (gate-diff, audit-export need enhancement)
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Conclusion
|
||||
|
||||
**Good News:**
|
||||
- ✅ 80% of UI infrastructure is complete
|
||||
- ✅ API wiring mostly done
|
||||
- ✅ Core graph visualization working
|
||||
- ✅ Backend APIs are complete and ready
|
||||
|
||||
**Action Items:**
|
||||
1. Complete Explainer Timeline (1-2 days) → Immediate visibility win
|
||||
2. Build Node Diff Table (2-3 days) → Critical comparison feature
|
||||
3. Polish existing components (1-2 days) → Professional finish
|
||||
|
||||
**Total Effort to MVP:** 4-7 days for P0 features
|
||||
|
||||
**Recommendation:** Focus on completing the 20-30% remaining work on existing components rather than building all new features. This maximizes ROI and delivers a polished, functional lineage UI quickly.
|
||||